Client : Trafalgar Housing Association
Location : Clydebank
Window Reinstallation Contract
The works comprised of the removal and reinstallation of 373 windows over 35 flats. Once the windows were removed they were reinstalled complete with new fixing brackets, DPC, external mastic sealant, new internal and external joiner work.
The Internal works in each flat involved the installation of new cills, facings, reveals and apron plates and final decoration of all joiner work. Externally, existing window flashings had to be re-installed / replaced, which required the use of a large Cherry Picker at high level. These works had to be carefully planned and co-ordinated to ensure that the works were completed safely, whilst maintaining access to all properties for tenants and visitors.
As all flats were occupied during the works which involved careful planning to ensure that we achieved entry to all flats in line with our programme. This was achieved by issuing newsletters at regular intervals advising on the progress of the works and be establishing clear lines of communication with our Head Office, which allowed tenants to discuss any concerns they had relative to the programme and scope of works.
Works were completed on time and for the majority of the properties in line with our original planned sequence.