PMC Commercial Limited has made significant progress on site at Motherwell Civic Centre over the past fortnight. Chiller cabling has been installed, the AHU cabling and shutdown are now complete, and the old chillers have been removed. The first phase of steel installation is finished, and works are already moving forward with commissioning of the AHUs and the commencement of waterproofing activities. The existing plinth is being removed, with second phase concrete repairs and steel installation also scheduled in the upcoming two weeks. The project remains on track as planned