Project

University of Edinburgh

Client : University of Edinburgh

Location : Edinburgh

Refurbishment and AV upgrade of University of Edinburgh Daniel Rutherford Building

PMC Commercial Limited were awarded the contract to carry out the works in April 2023 starting on site in May of the same year.

The works consisted of an initial soft strip and removal of internal fixtures and existing mechanical and electrical installations.

New floor, wall and ceiling finishes were installed as well as new perimeter .IN addition to this the existing mechanical and electrical installation was upgraded

The contract was carried out within the allocated 8 week period and handed over in late June of 2023.